Zeebrugge LNG plant (Zeebrugge, Belgium).
28 September 2023
LNG
Customer: Fluxys LNG
Service by: AMPO SERVICE Field Engineering Services
CHALLENGE:
Belgian natural gas operator FLUXYS LNG has requested several times valves commissioning services during plant construction and start-up to AMPO SERVICE.
SOLUTION:
AMPO SERVICE technicians have been on Belgium for several months and years (in different project phases) to support the technical staff of Fluxys LNG and help extend thousands of valves’ service life, supporting the cleaning process of the pipes, assembling internal valve components as well as actively participating in the commissioning and start up processes of the different phases of the project.
AMPO POYAM VALVES has supplied around 1,800 cryogenic butterfly valves and highly engineered ball, globe, gate and check valves for this project.
Other Case Studies
28 September 2023
LNG
Tianjin Polycarbonate Complex (Tianjin, China)
CHALLENGE: The 50-50 joint venture Sinopec Sabic Tianjin Petrochemical Co. Ltd (SSTPC) requested in…
Read more
28 September 2023
LNG
Pennsylvania Chemicals project (Potter Township, Pennsylvania, US)
CHALLENGE: The petrochemical complex (now Shell Polymers Monaca) is a world-scale facility that produces…
Read more
28 September 2023
LNG
SASA – PTA Production complex (Adana, Turkey)
CHALLENGE: SASA POLYESTER, one of the world’s leading manufacturers of polyester, fiber, filament yarn,…
Read more